May 092012
 

A contractor for the City of Palo Alto Utilities is currently installing a new 2″ gas main on Maybell Avenue. THIS WILL INCLUDE A CONNECTION TO THE GAS LINE SERVING THAIN WAY. For the present a connecting lateral line will be installed crossing Maybell up to the stop signb on Thain Way. The access pit will be covered by a steel plate.

At a later date the City of Palo Alto will connect the lateral to the EXISTING gas line on Thain Way. No installation of a new line on Thain Way is anticipated. We will be notified of the dates for this connection and whether or not it will be necessary to shut off gas service to complete the work.

NOTE: If it is necessary to shut off the gas service to complete the connection, then the Utilities Dept. will need to have access to your units to relight any pilot lights (furnace, hot water heater, etc) as needed. There is no need to take any further action at this time.